Who this checklist is for
-
The 7 steps
-
Step 1: Get the load figure from facilities in writing — don't calculate it yourself
-
Step 2: Decide whether you actually need a UPS
-
Step 3: Read the rating standard on the spec sheet — not just the kW number
-
Step 4: Know what "conditioning" hardware is actually in the quote
-
Step 5: Line-item the quote against the spec sheet — every line
-
Step 6: Verify invoicing capability before you place the order
-
Step 7: Plan the service contract on the day of order — not after the install
-
Step 1: Get the load figure from facilities in writing — don't calculate it yourself
-
Common mistakes I've seen (and one I made twice)
Who this checklist is for
I'm not an electrician, and I'm not a facility engineer. I'm the office admin who handles purchasing for a three-office company — I get the quote, check it against the requirement, walk it through finance, and then chase the delivery and the invoice. I've ordered two generators, rejected three quotes, and seen one arrive that didn't fit the pad it was ordered for.
This is the checklist I use now. Seven steps, roughly in the order I do them. The ones I learned the hard way are marked.
The 7 steps
Step 1: Get the load figure from facilities in writing — don't calculate it yourself
This is the one step where guessing gets expensive in a hurry. A 20 kW SDMO diesel generator covers a single small office plus a light server load. Moving up to a 35 kW Kohler SDMO unit isn't a small step — it's often a different electrical service, a different pad, and a different transfer switch class. Sizing wrong in either direction has a cost, and either way you're the one explaining it to finance.
The number you actually need is the running load in kW plus the largest motor starting load in kVA. I get that from the facilities engineer or the installing contractor, in writing, before I request any quotes. If someone hands you a single "we need about 30 kW" line, push back. That's not a spec, that's a guess with a decimal point.
One note on comparisons: the SDMO-generator range and a GE standby generator occupy different product categories. The GE standby line is aimed at residential and light-commercial loads — different enclosure rating, different run-time assumptions between service intervals. Comparing them strictly on price per kW is a category mismatch, not a like-for-like savings.
Step 2: Decide whether you actually need a UPS
A standby generator doesn't come online instantly. Depending on the transfer switch setup, you're looking at 8-15 seconds between grid loss and stable generator power. If your IT closet, phone system, or access control can't ride through 15 seconds, you need an uninterruptible power supply (UPS) in front of it — sized to bridge that gap, not to run the whole office.
These are not the same purchase and not the same quote line. A UPS is short-duration, high-quality power. A generator is long-duration, "good enough" power. If a vendor is selling you a generator as "backup for everything," ask what happens to the servers in the first 12 seconds. That question tends to reorganize the conversation.
Step 3: Read the rating standard on the spec sheet — not just the kW number
This is the step most people skip. A generator spec sheet should quote the rating standard, usually ISO 8528, and tell you whether the number is standby, prime, or continuous. A "35 kW Kohler SDMO generator" rated at standby is not a 35 kW continuous machine. It's a 35 kW emergency machine with a duty cycle attached.
What was fine on a 2019 spec sheet doesn't always pass in 2025. Modern UPS systems with active front ends, inverter-driven HVAC, and variable-speed drives all interact with generator waveform and harmonic distortion in ways older sizing guides didn't fully account for. If the vendor's quote and spec sheet were generated in 2021, ask for a current one.
Step 4: Know what "conditioning" hardware is actually in the quote
Power conditioner vs surge protector is a distinction that gets blurred in sales language, and it matters. A surge protector clips voltage above a threshold — it protects against spikes and nothing else. A power conditioner actively regulates the waveform, correcting brownouts, sags, and harmonic distortion on an ongoing basis. They're not interchangeable, and they're not redundant.
For an IT room or a lab, you likely want a conditioner on the sensitive loads. For the main panel, a surge protector is often the right answer. If the quote lists "protection" as a line item with no model number or spec, that's your cue to ask for both.
Step 5: Line-item the quote against the spec sheet — every line
I only believed this one after skipping it once and eating the mistake. The quote summary said "35 kW diesel generator, enclosure, pad, install." The spec sheet said the enclosure was rated for indoor use, and the pad was sized for the 20 kW frame. The unit arrived six inches wider than the pad. We paid the rigging fee and the re-pour, and I had a very short conversation with my VP.
Now I print the spec sheet, print the quote, and go line by line: kW, kVA, voltage, phase, fuel type, enclosure rating (NEMA 1 indoor vs NEMA 3R outdoor is a real price and code difference), pad dimensions, transfer switch model, exhaust configuration, warranty term, and the rating standard from Step 3. If any line on the quote doesn't match a line on the spec, the order doesn't get placed.
Step 6: Verify invoicing capability before you place the order
This one cost me $2,400 in rejected expense reports back in 2022. I found a good quote on a smaller generator for a remote site, placed the order, and then got a handwritten receipt and a handshake. Finance rejected it twice. I ended up covering it from the department budget and fighting the refund for three months.
Now I verify three things before any order over about $5,000: do they issue a proper itemized invoice with a tax ID, do they accept our PO format, and will they take standard payment terms or do they want a wire up front. If the answer to any of those is "we'll figure it out," that's not a vendor I'm placing an order with.
Step 7: Plan the service contract on the day of order — not after the install
The step everyone forgets. A diesel generator that isn't exercised and serviced isn't a backup — it's a metal box that might start. The service contract should be quoted at the same time as the unit, ideally from the same vendor or a tech on the SDMO service network if you're buying into that line.
Ask specifically: what's the exercise schedule, what's included in the annual service, what's the response time for a no-start call, and does the warranty require using a certified tech. If the vendor can't answer those in the quote phase, they won't answer them faster when the unit is down at 2 a.m.
Common mistakes I've seen (and one I made twice)
Three patterns, roughly in order of how often they show up:
- Sizing from the previous generator. "We had a 20 kW, so we'll get a 20 kW." That works until someone adds a server rack and a second HVAC unit. The load calculation is the load calculation.
- Treating the UPS and the generator as the same line item. They answer different questions. The generator asks "can we keep running?" The UPS asks "can we make it through the 12-second gap?"
- Ordering before confirming invoicing. Twice, in my case. It's a boring checkpoint right up until it isn't.
One thing I'm still not sure about: why the same vendor can quote a 48-hour lead time one quarter and a four-week lead time the next, with no obvious change to the spec or the in-stock position. My best guess is that it tracks to their factory allocation rather than anything customer-facing, but I've never gotten a straight answer. If anyone has a better read on that, I'd genuinely like to hear it.
The core of the checklist hasn't changed much in five years, but the inputs have — the rating standards are tighter, the load mix is harder, and the paperwork expectations on the finance side are higher than they used to be. That's the part worth updating every cycle.